Part 1You have been assigned as a project manager for a small construction compa

Get fast, custom help from our academic experts, any time of day.

Place your order now for a similar assignment and have exceptional work written by our team of experts.

✔Secure ✔ 100% Original ✔ On Time Delivery

Part 1You have been assigned as a project manager for a small construction company and have been assigned your first project. The client feels they have a basic grasp on their requirements but also feels that they will know more as the project progresses.  Using your knowledge of life cycle models, identify two models that may work based on your knowledge of the project.   The scope of the project is as follows: 
Requirement 1:  3 bedrooms
Requirement 2:  2.5 bathrooms
Requirement 3:  Pool 
Requirement 4:  2 patios, one patio should be enclosed
Using your experience documenting scope, outline the problem/opportunity statement you are trying to solve for, 2-3 success criteria, and any assumptions, risks, or obstacles.  Part 2Create a Work Breakdown Structure (WBS) for the following scope:
Requirement 1:  3 bedrooms
Requirement 2:  2.5 bathrooms
Requirement 3:  Pool 
Requirement 4:  2 patios, one patio should be enclosed
Your WBS should be based upon your chosen Life Cycle Methodology and include any deliverables. Part 3
Build a network diagram
Identify the early start, early finish, late start late finish for each activity
Identify the critical path
Identify the duration of the critical path
What is the float of Activity B
What is the float of Activity H
ActivityPredecessorDuration in DaysAStart3BStart6cA, B12DB5ED4FC6GE,F8HE7IH3

Get fast, custom help from our academic experts, any time of day.

✔Secure ✔100% Original ✔ On Time✔ No AI Content

Site Footer

Sliding Sidebar

Company

About Me

About Me

Lorem ipsum dolor sit amet, consetetur sadipscing elitr, sed diam nonumy eirmod tempor invidunt ut labore et dolore magna aliquyam erat, sed diam voluptua. At vero eos et accusam.

Social Profiles

Facebook